On 5th April, 2019, at 6:08pm UTC our engineers were alerted to an issue within our Amsterdam data center that resulted in a subset of workspaces becoming inaccessible.
We determined that a faulty connection within our infrastructure triggered a hardware reboot, making this set of workspaces inaccessible at 6:00pm UTC. Service was restored at 7:01pm UTC when the reboot process was completed, and we completed validation with customers to confirm their workspace access by 7:09pm UTC.
We have escalated this faulty response and identified corrective actions to prevent future recurrence of this issue, including a firmware upgrade to be implemented in an upcoming infrastructure update.